Nagpur :-The Central Railway’s ambitious redevelopment of Nagpur Station is progressing rapidly, with multiple key components of the project showcasing substantial advancement towards transforming the station into a state-of-the-art transportation infrastructure.
The comprehensive project, which encompasses the complete modernization of East and West station buildings, Foot Over Bridges (FOBs), a central concourse, and advanced facilities, is demonstrating steady progress across various critical construction phases.
*Project Highlights*
*East Station Building Developments*
Significant milestones have been achieved in the East Station Building, including:
Unified Basement: Final finishing work currently underway
EW-1 Arrival Building: Structural work completed up to the fifth floor, with 60% of terrace slab casting finished
EW-2 Departure Building: Slab casting completed, blockwork progressing on multiple floors
EW-3 Basement Parking: Foundation work at 20% completion, with extensive excavation and dismantling phases nearly complete
*West Station Building Progress*
The West Station Building is also witnessing substantial development:
WW-4 Admin Block: Slab casting completed up to the second floor, with ongoing column and beam work at higher levels
WW-3 Basement Parking:
Phase I: Structural work finalized, parking area handed over with finishing touches in progress
Phase II: Excavation 90% complete, foundation work approaching final stages
*Infrastructure and Connectivity Enhancements*
Critical infrastructure developments include:
Foundations completed for Central Concourse and North FOB on Platform 8
South FOB foundation excavation in active progress
Temporary overhead equipment (OHE) modifications underway at Goods Yard and platform locations
The redevelopment project aims to significantly enhance passenger experience and operational efficiency, aligning Nagpur Station with global standards. Central Railway remains committed to completing this transformational project on schedule.